Kronospan orders additional OSB plant core package from Dieffenbacher

Kronospan orders additional OSB plant core package from Dieffenbacher

New order is part of expansion and modernization project at Sanem site in Luxembourg

Kronospan plans on investing 330 million euros at its Sanem site in Luxembourg over the next four years. Before the planned new construction of a particleboard plant in the second project phase, the existing OSB plant will be partially refurbished and modernized.

The multi-opening plant, in operation since 1996, was one of the first OSB production plants in Western Europe. After more than 20 years of operation, it will be replaced by a continuous production line with CPS+. In addition to the press, the order also covers the forming station, the forming line, the finishing line (comprising a diagonal saw, large stack formation and large stack storage) as well as the conveyor technology, the filter systems and the press exhaust air treatment. The execution and supervision of the assembly are also included in the Dieffenbacher scope of supply.

This cutting-edge plant was planned entirely using 3D design tools. This allowed Dieffenbacher to fine-tune the plant structure to the conditions at the site, largely avoiding additional preparatory work for Kronospan. The contract was signed at the end of May, and commissioning is set for autumn 2018.

The project continues the long-standing collaboration between Dieffenbacher and Kronospan, especially in the area of OSB. Sanem will be the sixth OSB project completed by Dieffenbacher for Kronospan in less than 15 years. Kronospan also produces OSB panels using Dieffenbacher plants in Jihlava (Czech Republic), Riga (Latvia), Brasov (Romania), Mogilev (Belarus) and Strzelce Opolskie (Poland).

Para mayor informacion: http://dieffenbacher.vetas.com


WEMHONER Surface Technologies

IT MAY INTEREST YOU

Card image cap The only tree in the middle of the Sahara desert that was vital for commercial and military routes

The Ténéré Tree, a solitary acacia in the Sahara desert, became for centuries a beacon of life and reference for travelers In the vast Sahara desert, where aridity and silence dominate the landscape, there was a tree that stood alone, being a beacon of life and hope for travelers.

Read news »

Card image cap Between Rivers | Everything ready for the traditional INTA Concordia and AIANER Forestry Days

The traditional Entre Ríos Forest Days, which this year celebrate their 39th edition, will take place on November 7 from 8 a.m. to 6 p.m. at the INTA Concordia facilities, located at Yuquerí Station and Railway tracks.

Read news »

Card image cap Black River | Government and institutions promote a balanced development model between production and the environment in Valles Irrigados

Within the framework of the impulse that the Provincial Government has been giving to forestry policy, a joint tour was carried out between the Forestry Directorate of the Ministry of Economic and Productive Development, the Provincial Department of Water (DPA), the National Institute of Agricultural Technology (INTA) and the consulting firm Lygnum.

Read news »

CASTALY MACHINE

FARAM SRL

ROSARIO ABRASIVOS SRL

VIALRO

INGLAMIAUX

RAIES MADERAS S.A.

SAN VICENTE MADERAS SRL

KCD SOFTWARE

USNR

GRUPO EURO

PIERMATTEI S.A.

TRIPAYN SRL

CLARKE S INDUSTRIES Inc.

HUGO DANIEL VALETTO

SHOPBOT CNC TOOLS

LUAN - Ferroplastica Olivos S.R.L.

HERRAJES MANDILE

CORCHOLINEA

AUTOPERFORANTES TEL

EL EMPORIO DEL TERCIADO SA

THERMWOOD

TEPELCO S.A.